Progress Page: Live Budget Tracking & Actuals in Ontraccr

🧾 Progress Page: Live Budget Tracking & Actuals in Ontraccr


📘 Overview

The Progress Page in Ontraccr is your real-time command center for job costing. It compares your budgeted values (from Step 5) to the actual costs being recorded from field activity — including labor time, materials, and equipment usage.

This page is where you monitor whether your project is staying on track financially, across every cost code and category.


📊 What You’ll See on the Progress Page

Each cost code appears in a line-item table grouped under:

  • Labor
  • Material
  • Overhead
  • Equipment

For each cost code, Ontraccr displays:

ColumnDescription
Estimated CostFrom your budget
Estimated HoursOnly for Labor or Overhead
Actual CostPulled from time entries, materials, or equipment logs
Actual HoursFor time-tracked cost codes
Remaining CostBudgeted − Actual
Remaining HoursBudgeted − Actual
% CompleteActual ÷ Estimated (cost or hours)

🕒 How Actuals Are Calculated

  • Labor → from time entries (with cost code match + overrides)
  • Material → from material usage forms (with cost codes)
  • Equipment → from equipment logs (with code + rate)
  • Overhead → from time entries or form-driven overhead tracking

🧠 Example

Cost code: “LAB-01: Electrical Rough-In”

| Budgeted Hours | 100 |

| Logged Time | 60 |

| Remaining Hours | 40 |

| % Complete | 60% |

If the worker wage is $50/hr, and you’ve logged 60 hours, the actual cost is $3,000.


📌 Progress Page Behavior Notes

  • It only shows cost codes that have budgeted values
  • It includes only codes that were added to the project during setup (Step 3)
  • If no time/material/equipment has been logged, actuals = $0
  • Updating cost code overrides (e.g., wage or billing) affects future entries but doesn’t retroactively recalculate actuals

📤 Export Options

Click the three-dot menu (⋮) at the top right of the Progress Page to:

  • Export to Excel
  • Share or archive budget-to-actual comparisons
  • Filter by cost code category or completion %

📈 Reporting Tie-Ins

The Progress Page feeds directly into:

  • Time Card Reports
  • Project Dashboard widgets
  • Custom Analytics (via the Analytics Engine)

🧠 Tips

  • Review this page weekly to catch cost overruns early
  • Sort by % Complete to identify tasks at risk
  • If a cost code is fully billed but not 100% complete, it may indicate missing time/material entries